EPZA Projects

Total Projects Prepared by Ministry / Division : (Private investment )

Sr. No. Name of Project Milestones (Specimen – To be modified according to requirements of the project) Responsibility Timeline Remarks
1

Infrastructure Development Works of Karachi Export Processing Zone Phase-III on basis of Charges development from Investor .

Estimated Investment Required

Rs.2626.00 Million

i. Concept proposal / Pre Feasibility EPZA, MOI&P 3 Months The time line will start from date of approval of PC-I of the proposed project from appropriate forum
ii. RFP Preparation EPZA 3 Months
 iii. Tender EPZA 2 Months
iv. Evaluation EPZA, Federal MOI&P 3 Months
v. Award EPZA, Federal   MOI&P 3 Months

 

Total Projects Prepared by Ministry / Division : (BOT Mode)

Sr. No. Name of Project Milestones (Specimen – To be modified according to requirements of the project) Responsibility Timeline Remarks
1

Infrastructure Development Works of Gwadar EPZ on BOT Basis.

Estimated Investment Required

Rs.7.025 Billion

✓ Concept Proposal / Pre-Feasibility / PC I Preparation EPZA, MOI&P 2 Months The time line will start from date of approval of PC-I of the proposed project from appropriate forum
✓ Approval of PC-I EPZA/ MoIP/ Ministry
of Planning
Development and
Special Initiatives
(NPO/MoIP/MoPDSI)
2 Months
✓ Hiring of Project Staff & Appointment
of Consultants(If Any)
EPZA 2 Months
✓ Tenders, Evaluation, Award EPZA, MOIP 2 Months
✓ Execution of Project EPZA through DWP 2 Months
✓ Monitoring, Review & Evaluation of
Project
MoIP/MoPD&SI 3 years

Updated on 19/05/2020