EPZA PROJECTS
TOTAL PROJECTS PREPARED BY MINISTRY / DIVISION : (PRIVATE INVESTMENT )
Sr. No. | Name of Project | Milestones | Responsibility | Timeline |
---|---|---|---|---|
1 | Infrastructure Development of Karachi Export Processing Zone Phase-III on basis of advanced development charges from Investor.
Estimated Investment Required Rs.2.626 Billion |
i. Concept Proposal / Pre-Feasibility / PC I Preparation | EPZA | 2 Months |
ii. Approval of PC-I | EPZA/ MoIP/ Ministry of Planning Development and Special Initiatives / Finance Division | 2 Months | ||
iii. Hiring of Project Staff & Appointment of Consultants (If Any) | EPZA | 2 Months | ||
iv. Tenders, Evaluation, Award | EPZA | 2 Months | ||
v. Execution of Project | EPZA | 3 Months | ||
vi. Monitoring, Review & Evaluation of Project | MoIP/MoPD&SI | Quarterly |
TOTAL PROJECTS PREPARED BY MINISTRY / DIVISION : (BOT MODE)
Sr. No. | Name of Project | Milestones | Responsibility | Timeline |
---|---|---|---|---|
1 | Infrastructure Development Works of Gwadar EPZ on BOT Basis.
Estimated Investment Required Rs.7.025 Billion |
i. Concept proposal / Pre Feasibility | EPZA, MOI&P | 3 Months |
ii. RFP Preparation | EPZA | 3 Months | ||
iii. Tender | EPZA | 2 Months | ||
iv. Evaluation | EPZA, Federal MOI&P | 3 Months | ||
v. Award | EPZA, Federal MOI&P | 4 Months |